We are offering
Our specialists offer knowledge and experience gained from a wide range of process technologies and projects undertaken in the past.
Construction and commissioning of new semi-dry flue-gas treatment system (including condensation heat-recovery and auxiliaries) belonging to project of new biomass-fired power plant HOFOR BIO 4. Project was done in cooperation with LAB S.A.. Plant is designed as high-efficiency low carbon emissions power plant with special focus for city district heating. Project was done for Danish company HOFOR.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Construction and commissioning of new Flue-Gas Heat Recovery system on Herning Poer Station (1 unit) belonging to project of plant modernisation. Project was done in cooperation LAB S.A. (Process Plant supplier). Plant is designed as high-efficiency low emissions power plant with special focus for city district heating. Project was done for Danish company Ørsted as the final client.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Construction and commissioning of new FGT plant (2 units) belonging to project of new waste incineration power plant Amager Bakke. Project was done in cooperation of Babcock-Wilcox Volund (2x boiler); LAB S.A. (Flue-Gas treatment) and SIEMENS (Steam Turbine). Plant is designed as high-efficiency low emissions power plant with special focus for city district heating. Project was done for Danish company RAMBOL and final client A-R-C.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
First European Power plant that was successfully relocated from Voitsberg in Austria. AUTCOM’s contractual partner for commissioning works was Škoda Praha a.s.. Works started January 2017 and finished July 2018. The final client was ODAS Enerji Turkey.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
AUTCOM was involved in design phase as an consultant for C&I systems on Coal and Ash handling system. The whole system was designed and delivered by Vitkovice Gear Works.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Complete replacement of 5 units of existing HRSGs for new 228 tons/hr HRSG units (retaining existing GE gas turbines) was done by Deutche Babcock – Bilfinger Babcock. Along with HRSG units the BOP systems (feed water system and electrical switch-yard) were replaced as well. The whole plant was integrated in to existing process steam distribution system. GE Mark VIe was used as DCS system for whole plant. New DCS was fully integrated in to existing plant control system. Whole project was done under supervision of L&T Sargent & Lundy.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Reconstruction of units 40 and 50 to combined cycle with gas-oil SIEMENS turbine and HRSG Babcock Borsig Steinmüller (originally AE&E). Steam turbines were preserved original (ESCHER WYSS). There was implemented a complete replacement of piping, I&C equipment and DCS and a part of the machinery has been maintained. The contract was carried out between 2011 and 2012 in collaboration with EPP Ankara, SIEMENS Germany and BBS Brno. The final client was EUAȘ Ankara.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Construction and start-up of new technology of wet desulphurization (2 units FGD) for boilers 1 to 8 with common operation of up to four boilers in one unit FGD. The contract was carried out between 2011 and 2012 in collaboration with Austrian Energy & Enviroment Graz, later Andritz Energy & Enviroment Graz, Austria.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Construction and start-up of new technology of wet desulphurization of units I., II., III. and IV. The contract was carried out between 2010 and 2011 in collaboration with Austrian Energy & Enviroment Graz, later Andritz Energy & Enviroment Graz, Austria.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Running and testing a new supercritical boiler for the block 750MW. The contract is implemented from 2011 up to now in collaboration with IHI, Japan and TRIANEL
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Commissioning and testing the new 930MW combined cycle power station (2+1 configuration). The contract was carried out between 2010 and 2011 in collaboration with A-TEC, Austria and MHI, Japan. The final client was ENERJISA, Sabanci Group, Turkey.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Construction and start-up of new technology of wet desulphurization (FGD 3 units) for 500MW units 2 to 4. The contract was carried out between 2009 and 2010 in collaboration with Austrian Energy & Enviroment, Germany and Lentjes UK. The final client was SSE Perth.
During start-up phase AUTCOM executed:
AUTCOM positions on project:
Construction and start-up of new technology of wet desulphurization (FGD 3 units) for 320MW units 1 to 3. The contract was carried out between 2001 and 2005 in collaboration with Babcock & Wilcox, USA. The final client was EUAȘ Ankara.
During start-up phase AUTCOM executed:
AUTCOM positions on project: